ERCOT just released its October report, and the most important slide is about data centers.
Texas has approved 9,456MW of large loads, mostly data centers, to connect to its grid. For nine straight months, about 4,000MW of that was actually running. In October it jumped to 5,115MW, the biggest monthly increase on the chart.
The other half of the chart is what matters. Total approvals barely moved all year, from 8,786MW last December to 9,456MW today. And there have been zero new approvals since August. Texas froze new large-load hookups while it re-studies a queue of roughly 200GW of requests, and the results don’t go to regulators until December 17.
So the data centers already approved are ramping fast, but only about 4,300MW of approved room is left before the cap hits.
Meanwhile, supply is flooding in from the other side. Batteries are now the biggest category in ERCOT’s queue at 160GW, with about 87GW scheduled for 2027 and 2028 alone. Gas projects mostly don’t show up until 2029 to 2032, which is how long new turbines take.
The forward market is pricing exactly that. 2027 Texas power is trading near $41/MWh, down from about $65 a year ago. 2031 is near $58, barely changed. Cheap now, tight later.
Record demand, frozen approvals, and a wave of batteries add up to one thing: the near-term Texas power trade isn’t about generators getting paid more. It’s about who gets through the approval gate on December 17, and who doesn’t need the grid’s permission at all.
JPM Data Center Power Expert Call
1. Gas turbines are in short supply, creating opportunities for alternatives. The expert favors 20–60MW industrial and aeroderivative gas turbines for on-site generation, but deliveries of new units may stretch into 2030 or beyond. This is driving interest in reciprocating gas engines, fuel cells, refurbished turbines and battery storage. Fuel cells can be deployed faster and produce lower emissions, but cost more.
2. Self-supplied power could become a long-term asset rather than a temporary solution. The expert recommends designing projects for an eventual grid connection from the outset: use on-site gas generation initially, then retain it for backup power and export surplus electricity when the grid is under stress. In one example, a 500MW IT load could be supported by roughly 700MW of gas generation, reducing the need for traditional diesel backup generators. Grid connection itself can take four to six years or longer.
3. Local opposition is a real development risk. Residents are concerned about electricity prices, water use, emissions, noise and local economic benefits. The expert cited roughly 385 data center project delays or cancellations this year, versus about 50 last year; the report does not independently verify those figures. Cleaner equipment, alternative cooling systems and community investment may help address opposition, but add costs. Developers may also shift projects to other regions.
4. Equipment suppliers have strong pricing power, while developers are taking on more upfront risk. Multiyear lead times allow suppliers to pass through commodity, tariff and freight costs and secure long-term service agreements. To lock in supply, developers sometimes buy major equipment before projects receive final approval. Shortages of electricians, HVAC technicians and other skilled workers can further delay construction.
Recent gas-power deals and equipment quotes span ~$430–$2,500/kW, depending on the equipment and scope:
•LS Power / NRG: $4bn for 4.9 GW → ~$820/kW. Six existing plants spanning combined-cycle, simple-cycle and steam units, including sites, permits and grid connections.
•Anthropic / OnePWR: Reported $3.4bn for 1.7 GW → ~$2,000/kW. Caterpillar gas-generator commitments plus engineering/construction capabilities, per the FT.
•Caterpillar’s Solar Turbines: Two used 14.5 MW units sold for $12.5m → ~$430/kW. New equivalents would cost ~$35m for the pair → ~$1,200/kW, with a five-year delivery time, according to ReflowX via Reuters.
•Broader turbine market: Reuters quotes ~$1,300/kW refurbished, ~$1,500–$1,700/kW well-maintained used and ~$2,000–$2,500/kW new. Equipment prices, before the broader plant-build costs.
Going to sound like I’m beating a dead horse but no matter how many people want to pretend like it’s some massive tidal shift, this was already the direction of travel and HAPPENING.
Reminder: OpenAI has REPEATEDLY committed to covering the energy and infrastructure costs of its data centers. Versions of the ratepayer-protection promise go back to at least October 2025.
The chronology ahead of today’s announcement:
>Oct 30, 2025, Michigan: Required upgrades would be funded by the project, with no cost passed to local ratepayers.
>Jan 20, 2026, Stargate Community: “we commit to paying our own way on energy, so that our operations don’t increase your electricity prices.” Each site would have a locally tailored community plan.
>Mar 4, Ratepayer Protection Pledge: OpenAI joined six other companies in committing to cover new power supply and delivery infrastructure, including paying for contracted power and infrastructure whether used or not.
>Jun 1, Michigan groundbreaking: Reiterated that the project would pay for its infrastructure and energy, protecting local residents from higher electricity bills because of the project.
>Jun 3, public policy agenda: Supported mandatory large-load tariffs requiring data centers to pay the incremental costs they create, alongside transparency on electricity, water and government agreements.
>Jul 22, Georgia: Committed to paying full infrastructure and electric-service costs, $80M in community benefits and an independent annual public audit.
>Aug 7, Texas: Committed to fully funding project-driven infrastructure costs without shifting them onto residential or small-business customers.
>Aug 17, Ohio: Said SB Energy would cover the full cost of required grid upgrades and new transmission lines. OpenAI committed another $40M to community priorities.
>Nov 2, Grid Protectors: Repeated the cost-coverage commitment while launching a national demand-flexibility program.
Today’s National Community Compact formalizes a broader framework for future campuses OpenAI owns and operates: published construction plans, site-level electricity and water reporting, independent noise studies, annual progress reports and financial assurances before major spending. It also restricts NDAs with public officials, allowing narrow protections for sensitive information.
The commitment to pay dates back well before today. The additional substance is in the specificity of the commitments and how communities can track delivery.
Going to try this again today... since Michael (who runs Cleanview) has a similar view on once you pass vertical construction.
Aterio’s Nov 5 snapshot lists 86.7 GW of US data centers under construction. 50.0 GW is at vertical construction or beyond; 22.5 GW is above 75% complete! Aterio’s first-steel milestone is 20%; above 75% generally means late equipment installation and fit-out.
Big blue wave states that people are concerned about - TX, GA, OH, IA, WI and PA account for ~45% of US construction and ~60% of that capacity has already reached vertical or beyond!
Ok what about the counties with passed, binding November restrictions? They contain <5% of US construction. Even still, within that footprint, 80% is vertical or beyond and 53% is above 75% complete. Whole-county totals include sites outside the voting municipality.
TLDR: There is already a large physical buildout to energize that is ALREADY in motion and are very large 20+ GW annual figures (mid-to-high teens GW 2026 +10GW 2025) that max out FTM and consider some BTM for line of sight in 2027 and 2028. Remaining power and permit approvals can affect delivery timing but that is not stopping or being cancelled at high levels.
You can keep freaking out on about 2028+ tbf, but there's plenty to keep hands full through 2028 on just the active pipe alone. Dems and Rs are proposing a lot of the same data center guidelines and I guarantee there'll be compromise before then vs. blanket moratoriums/cancellations some are concerned about. So new permits will be impacted but there will be reasonable paths forward. The sky is not falling out if you were underwriting reasonable numbers.
If you were underwriting much higher than that, you were always contemplating BTM + a lot of new gas generation in a way that already required some aggressive assumptions - at least to historical cadence. We shall see about that. On with your days...
The governor-elect of Texas, Gina Hinojosa, has explicitly said that all currently permitted datacenters in Texas will be allowed to finish construction. This essentially covers all of the 2027 and likely well into 2028.
She is going to pass laws that ensure that all *newly* permitted datacenters going forward for delivery in 2028/2029 will pay taxes, commit to no increase in power prices for consumers, don’t impact water availability for people, be constructed with union labor and give “Texans a seat at the table.”
Sounds reasonable. She doesn’t want to lose a lot of good blue collar jobs and property taxes for small towns in rural Texas.
Datacenter commentary starts at 6:30 in this interview.
Also attaching her official campaign position from her website in the next post.
Sidenote: After watching a bunch of her speeches and interviews, I do think she is a political talent and probably has a future in national politics.
https://t.co/shCGNcdu9d
Microsoft reportedly declined roughly 500 MW at Nscale’s own Ward County site. Its existing approximately 240 MW agreement at the adjacent Ionic Digital site remains. The FT says the rejected option was excluded from Nscale’s $103B backlog; both companies declined comment.
This follows a separate, confirmed cancellation in Essex. Microsoft withdrew after grid delays pushed power availability into the 2030s
Evercore ISI: DC Capacity Pricing
> GPU cloud providers with available capacity are now charging $30–50M/MW+ for compute capacity (exemplified by recent SPCX deals with Anthropic/GOOGL at ~$30–50M/MW and CRWV at ~$40M/MW for short-dated contracts), a sharp increase from the historical $10–15M/MW.
> Data center operators typically charge ~$2M/MW (assuming ~$200/kW per month lease pricing).
> Cloud providers monetize each MW at 5–17x what they pay for data center capacity.
> AI labs monetize each MW at >50x more than data center operators, with full-utilization inference monetization reaching upwards of $100M+/MW and potential up to $300M/MW.
$GOOGL $SPCX $NBIS $MSFT $ORCL $AMZN
I had Claude go through sell side reports, company filings, commentary etc. to build a rough supply/demand model for AI.
If you assume ~90% of TSMC incremental capex is leading edge, convert that into GW, convert that into tokens you get supply one way. Hyperscaler spending w/ a lag gives you another. The two aren't that dissimilar.
Demand is much harder to pin down. Can look at Google API traffic they report. Anthropic compute spend probably a low estimate since it reflect supply unlock rather than demand. Muse, Instinct, open source demand a little harder to pin down but they're additive.
Make adjustments to supply looking at chip specs over the next few years to turn GW into tokens.
Swing is probably demand more than supply. I assume for demand growth we just keep adding it at the same pace going forward but that mechanically slows growth. Accounts for penetration gains, but not really any new killer products.
Point is, we're short, we're going to get less short unless demand picks up. Generally markets getting less short is not helpful for their prices, but in this case, if token prices continue to fall as supply is unlocked, and that's passed on to consumers, the real key swing factor is Jevons and what degree of elasticity the market really has. Supply unlock could be bullish if it's high, could be bearish if it starts to taper off.
I am shocked, absolutely shocked, that Anthropic ARR has likely gone vertical in October after they cut token prices.
Except the exact same thing happened for the entire AI market, which is why GPU rental prices have surged while token prices declined.
$100b plus in year-end ARR looks possible again.
One answer to what's driving GPU rental prices:
Token demand on OpenRouter is up ~27x since last November, from ~6T/week to ~165T/week
Open-weight models now handle ~72% of those tokens, up from ~28% last November
Charts of the Week: https://t.co/BKHzpgt05x
Zooming out, GPUs are still renting ahead of a standard 6-year depreciation schedule
Rental price vs. schedule:
- H200: +143%
- B200: +111%
- RTX PRO 6000: +73%
- H100: +54%
- A100: +9%
Most of the gap opened up after April, when token demand took off
Charts of the Week: https://t.co/KJWFSaIGCd